Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73354 REL 6: 2008-524-00 EXP IMPLEMENT TRIBAL PACIFIC LAMPREY REST (CRITFC)
Project Number:
Title:
Implement Tribal Pacific Lamprey Restoration Plan
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Lower Columbia Willamette 100.00%
Contract Number:
73354 REL 6
Contract Title:
2008-524-00 EXP IMPLEMENT TRIBAL PACIFIC LAMPREY REST (CRITFC)
Contract Continuation:
Previous: Next:
75896: 2008-524-00 EXP IMPLEMENT TRIBAL PACIFIC LAMPREY RESTORATION
  • 73354 REL 24: 2008-524-00 EXP IMPLEMENT TRIBAL PACIFIC LAMPREY RESTORATION
Contract Status:
Closed
Contract Description:
This contract is directed toward implementing preliminary work leading to addressing the elements and recommendations within the Columbia River Inter-Tribal Fish Commission (CRITFC) Tribal Pacific Lamprey Restoration Plan for the Columbia River Basin (CRITFC 2008).  Among other things, recommendations include evaluating and fixing passage barriers such as those found in mainstem and tributary dam fishways and passage structures, and tributary water diversions, and developing tools to assess juvenile and adult lamprey passage, habitat, and life history.  Objectives include obtaining a better understanding of lamprey genetics and population substructure as well as an evaluation of appropriate populations for use in artificial propagation.
Account Type(s):
Expense
Contract Start Date:
05/01/2018
Contract End Date:
04/30/2019
Current Contract Value:
$594,039
Expenditures:
$594,039

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Applicable permits and other environmental clearances received A: 165. Obtain Environmental Clearance - NEPA, ESA, etc. 04/30/2019 04/30/2019
Technical report summarizing the use a multifunctional SNPs panel for genetic monitoring B: 162. Use a multifunctional SNPs panel for genetic monitoring of CRB lamprey species 04/01/2019 04/01/2019
Technical report summarizing the use a multifunctional SNPs panel for genetic monitoring C: 157. Genetic monitoring of CRB lamprey species - adult lamprey tissue collection 04/01/2019 04/01/2019
Technical report summarizing the use a multifunctional SNPs panel for genetic monitoring D: 157. Genetic monitoring of CRB lamprey species - pre-adult lamprey tissue collection 04/01/2019 04/01/2019
Technical Report summarizing results of 2018 adult and juvenile surveys in the Snake R. Basin E: 157. Determining the presence/absence of Pacific lamprey in the Snake River Basin 04/30/2019 04/30/2019
Facilitate the collection of adult lamprey from the Columbia River F: 66. Facilitate the collection of adult lamprey from the Columbia River 04/30/2019 04/30/2019
Technical report summarizing results of USGS lamprey contaminant research. G: 162. Assess emerging and legacy contaminants in Pacific lamprey in the CRB 04/30/2019 04/30/2019
Technical report summarizing utilizing existing datasets to address critical uncertainties H: 162. Utilizing existing datasets to address crtical uncertainties 04/01/2019 04/01/2019
Regional coordination with CRITFC member tribes regarding Pacific lamprey I: 189. Regional coordination with CRITFC member tribes regarding Pacific lamprey 04/30/2019 04/30/2019
Columbia River Basin regional lamprey coordination J: 189. Regional coordination of matters concerning Pacific lamprey 04/30/2019 04/30/2019
Various presentation(s) explaining Tribal perspectives and life history of Pacific lamprey K: 99. Outreach and education regarding Pacific lamprey to regional agencies and schools 04/30/2019 04/30/2019
NPCC "Three-Step Review" type document for lamprey "supplementation" research L: 174. Development of a NPCC "Three-Step Review" type document for lamprey "supplementation" research 04/01/2019 08/31/2018
All administrative tasks fulfilled with timely quality products M: 119. FY 2018 contract and budget management 04/30/2019 04/30/2019
Completed Annual Report CY17 N: 132. Submit Progress Report for the period 1/1/2017 to 12/31/2017 09/01/2018 09/28/2018
Completed Annual Report for CY18 O: 132. Submit Progress Report for the period 1/1/2018 to 12/31/2018 04/30/2019 04/30/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 174 Produce Plan
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Environmental Clearance - NEPA, ESA, etc. 05/01/2018
B 162 Use a multifunctional SNPs panel for genetic monitoring of CRB lamprey species 05/01/2018
C 157 Genetic monitoring of CRB lamprey species - adult lamprey tissue collection 03/21/2018
D 157 Genetic monitoring of CRB lamprey species - pre-adult lamprey tissue collection 05/01/2018
E 157 Determining the presence/absence of Pacific lamprey in the Snake River Basin 05/01/2018
F 66 Facilitate the collection of adult lamprey from the Columbia River 05/01/2018
G 162 Assess emerging and legacy contaminants in Pacific lamprey in the CRB 05/01/2018
H 162 Utilizing existing datasets to address crtical uncertainties 05/01/2018
I 189 Regional coordination with CRITFC member tribes regarding Pacific lamprey 05/01/2018
J 189 Regional coordination of matters concerning Pacific lamprey 05/01/2018
K 99 Outreach and education regarding Pacific lamprey to regional agencies and schools 05/01/2018
L 174 Development of a NPCC "Three-Step Review" type document for lamprey "supplementation" research 05/01/2018
M 119 FY 2018 contract and budget management 05/01/2018
N 132 Submit Progress Report for the period 1/1/2017 to 12/31/2017 05/01/2018
O 132 Submit Progress Report for the period 1/1/2018 to 12/31/2018 05/01/2018
P 185 Periodic Status Reports for BPA 05/01/2018